Your general contractor sends a final lien waiver with the latest pay application. The work covered by that application is complete, but retainage and a change order are still unpaid. Which form should you sign? Start by asking whether the payment closes out your entire account or pays for only part of your work.
Use a partial lien waiver for a progress payment and a final lien waiver when payment settles the covered scope in full. Then check the payment status. A pending payment typically calls for the applicable conditional form. An unconditional form should wait until you’ve confirmed receipt of the covered funds.
A construction lien waiver is a legal document that gives up specified lien rights. Depending on the form and applicable law, it can also release payment bond claims and other payment rights. Owners, lenders, and general contractors may require lien waivers to document which work a draw covers and which claims can still affect the project.
Progress waivers cover payments made along the way. A subcontractor may submit one with each monthly pay application. A supplier may use a partial waiver for a payment tied to a group of invoices or deliveries. More than one progress waiver can be appropriate on the same construction project as successive payments come due.
Match the waiver form to the work the payment covers. Compare it with the pay application and any attached invoice or schedule. If the payer sends less than the amount requested, reconcile the difference before you sign. Some forms can reach beyond the amount received if their wording covers a broader period or scope. Future payments, unpaid retainage, and work outside the release may still carry lien rights, depending on the form, the law, and whether you meet the relevant deadlines.
A final waiver covers the payment intended to close the account for the scope identified in the form. Before agreeing that a payment is final, reconcile your contract balance against prior payments, approved change orders, credits, and retainage. Review disputed extras or deductions with the payer. A closeout request can arrive while a balance is still open.
If the payer owes retainage or a change order is unresolved, ask for a waiver that fits the current payment and have counsel review any proposed release of the remaining lien rights. Signing a final waiver too early can give up rights you may need to collect an unpaid balance. Even a conditional final lien waiver can have that effect once its payment condition is satisfied.
The difference between conditional and unconditional lien waivers is when the release becomes effective: a conditional waiver depends on the specified payment, while an unconditional waiver states that payment has already been received and contains no future payment condition.

Texas Property Code §§ 53.281 and 53.284 set out the framework for statutory lien waivers on covered projects. For the ordinary progress and final payment process, use a waiver and release that substantially complies with the applicable statutory form. The claimant or an authorized agent signs it, and a conditional release requires evidence of payment. Section 53.283 prohibits requiring a claimant to sign an unconditional waiver and release for a progress or final payment before the claimant receives that amount in good and sufficient funds.
Texas progress forms describe the work by reference to the attached statement or progress payment request. They exclude unpaid retainage, pending modifications and changes, and other items outside the covered request. Check the attachment before you sign. The final forms address the covered job more broadly, so reconcile open items before using them. These forms can reach beyond a mechanic’s lien to payment bond rights and other claims for payment.
The Texas conditional forms are written around check payment. For a check, the conditional waiver takes effect once the specified check is received, properly endorsed, and paid by the bank on which it was drawn. If the parties use ACH, a wire, or another method, have counsel confirm the appropriate form and evidence of payment. Texas’s rules apply to Texas projects. Other states may prescribe different forms, exceptions, and requirements about what the waiver covers.
A supplier completes its final delivery on a Texas job. The general contractor approves the current draw and sends a check, but still holds retainage. The supplier checks the invoices covered by the draw and uses the applicable conditional progress waiver for that payment. It records which invoices the check pays and confirms when the check clears. If the general contractor then requests an unconditional progress waiver, the supplier matches it to the same draw.
When the retainage and any remaining balances are ready for payment, the supplier reconciles the entire account before considering a final waiver. The shipment date tells the supplier when delivery ended. The account records tell it when the payment is actually final.

Good lien waiver management puts the waiver, supporting pay application, and payment status in the same record for each draw. At closeout, use that record to check which construction payments have been received and which amounts are still open.
If a payment stalls, a waiver asks you to release more than you expected, or a notice deadline is approaching, gather your contract, pay applications, payment records, and signed waivers. Our construction lien services can help you assess the project records and discuss timely options for protecting your payment rights.